Aktote Kairan Project

  • Client ENI
  • Activity Conceptual study for process design
  • Year 2013
  • Hours Committed 6.500

Basing on available production profiles the Customer awarded DG IMPIANTI with the scope to carry out the conceptual study for the filed development basing on 12 possible scenarios. Within such frame, DG IMPIANTI investiagtes all possible configuarion in order to identify the suitable cost effective solution to revore and treat the maximum hydrocarbons quantities.

The DG process team, has been working for several months in order to carry out all possible simulations (12 scenarios) and evaluating all energy and material balance with both a technical and an economical approach. Two possible solutions have been adressed as best options to the Customer and OPEX and CAPEX estimation has been carried out by internal estimation department. All process simulations have been carried out by the use of HISYS and PRO II softwares, whilt a probabilistich approch has been carried out by Oracle Crystal Ball for cost estimations.